What is the initial storage capacity per acre for a sediment trap?

Enhance your knowledge for the Stormwater Erosion and Sedimentation Control Exam with practice questions, flashcards, and in-depth explanations. Prepare effectively for your test!

The initial storage capacity per acre for a sediment trap is defined as 134 cubic yards. This volume is based on the need to efficiently manage sedimentation during construction activities. Sediment traps are designed to capture runoff and prevent excess sediment from leaving the construction site, which is essential for protecting water quality and minimizing the environmental impact of soil erosion. The specific figure of 134 cubic yards serves as a standardized benchmark used in erosion and sediment control plans to ensure that sediment traps can sufficiently handle expected runoff volumes while maintaining their effectiveness. This metric is critical for engineers and project managers when designing and implementing appropriate stormwater management practices.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy